Sheet pile
Interlocking metal sections that are connected to each other to form a continuous retaining wall.
Design and build of a launching facility.
The Dubai Drydocks naval shipyard has extended its capacities by commissioning a hydrolift for the construction and repair of floating equipment. This structure was entirely completed by Soletanche Bachy acting as the main contractor under a design and build contract.
Dubai drydocks
Royal Haskoning
Soletanche Bachy en groupement avec NSCC
07/08/2005 - 09/07/2006
The launching facility acts as a lift between sea level and the dock water level. It enables the vessel to be moved vertically and horizontally and acts like a slipway but incorporating a reverse hydraulic process.
THE STRUCTURE COMPRISES:
The conforming design envisaged sheet pile wall held by ground anchors to form the basin. Soletanche Bachy came up with an alternative solution that replaces the sheet piles with diaphragm walls. The diaphragm wall was mostly cantilever and was constructed with T panels. The wall along the transfer platform was constructed using flat panels.
300,000m3 of sand was first brought in to make a working platform for the land construction of the diaphragm walls and pile installation. Diaphragm walls were constructed all around the basin and also along the perimeter of the two abutments. A sheet pile cofferdam, connected to cast-in clutches in the diaphragm wall, was constructed between the abutments, to allow the construction of the sill and the abutments in the dry. The sill was founded on barrettes and concrete piles.
Dewatering of the sill and abutments was achieved with 10 deep wells. All works were done in the dry. Cast-in couplers were used to connect the diaphragm wall to the abutment structure. Leaving a bund at the sea end allowed the basin excavation in the dry. Dredging to final depth was then carried out inside of the basin. The transfert platform is founded on CFA piles.
A diaphragm wall is a support of excavation technique used by Soletanche Bachy for almost 60 years.
Interlocking metal sections that are connected to each other to form a continuous retaining wall.
Piles in concrete, steel or wood (or a combination of these materials) installed by pile-driving.
Soletanche Bachy is a world leader in foundations and soil technologies, operating in 60 countries via a network of 80 subsidiaries and branches. The Group delivers the full range of geotechnical processes and provides innovative, effective solutions as either a lead or specialist contractor for turnkey projects with a geotechnical focus or specialist works.
This website uses cookies to ensure you get the best experience
Learn more